Brazil Wants to Restart Work on Nuclear Plant Paralyzed in 1988

The director of Planning, Management and Environment at Eletronuclear – the Brazilian company that operates the Angra 1 and 2 nuclear power plants – LuÀ­s Hiroshi Sakamoto, says that Brazil will need another nuclear power plant to meet the demand.

That nuclear power plant is Angra 3, which, along with Angra 1 and 2, went into construction during the military administrations (1964-85).

Angra 1 and 2 have been completed and are operational, but Angra 3, scheduled to be operating in 1988, was never finished although US$ 750 million was spent on it.

It is estimated it costs US$ 20 million just to maintain it in its present state, and will take another US$ 1.8 billion and five years to complete.

All three of Brazil’s nuclear power plants are located closely together at a beach resort, Angra dos Reis, on the coast of the state of Rio de Janeiro 150 kilometers from the city of Rio de Janeiro.

Sakamoto points out that because they are clean, the use of nuclear power plants around the world means that two billion tons of carbon dioxide have not been pumped into the atmosphere, aggravating the greenhouse effect.

As for Angra 3, Sakamoto says Brazil has the know-how to conclude the construction and is ready to do so. "The country is going to need more energy and Angra 3 is an obvious candidate to supply it," he said.

The Brazilian official added that the fact that construction on it has already begun is a positive point. "What has been paid for is paid for. We will move ahead from where we are. There is no need to start from scratch. It means building Angra 3 will cost less than a similar plant anywhere in the world."

Sakamoto says that at the moment nuclear power (Angra 1 and 2) supplies 40% of the electricity used in the state of Rio de Janeiro. With Angra 3 in operation, that percentage will rise to 70%.

Agência Brasil

Tags:

You May Also Like

A Brazilian Water-Sports Brand Gets a Place Under Global Sun

Mormaii, the main Brazilian neoprene surf clothes and water-sports brand, sells it products in ...

Mexican Brewery Buys Brazil’s Kaiser from Molson Coors

Fomento Economico Mexicano, S.A. de C.V. (Femsa) announced that its wholly owned subsidiary Femsa ...

Entrepreneur’s Fair 2.0 Comes to Brazil

Brazil’s Entrepreneur’s Fair to be held in Minas Gerais state has two main objectives, ...

Brazil: A Few Stereotypes of My Own

In Brazil, if you are dating, you let the entire world know it. You ...

Sometimes You Need an Englishman to Teach the Brazilian Art of Capoeira

Every nationality carries its own stereotypes, and sometimes they happen to be true. If ...

Brazil Hopeful the Amazon Will Be Deemed Free of Hoof and Mouth Disease

According to the Brazilian Ministry of Agriculture, Livestock, and Supply, Brazil is about to ...

While Rich Cut Social Benefits We’re Investing More, Says Brazil’s Finance Minister

Brazil’s Minister of Finance, Guido Mantega, informed that the Brazilian government will raise its ...

Brazilian Chicken Exports to Middle East Grow 17%, Bring 66% More Revenue

The volume of Brazilian exports of chicken to the Middle East should break a ...

Fidel Paid for Lula’s Presidential Campaign, Says Brazil’s Leading Magazine

Brazilian  President Luiz Inácio Lula da Silva seems to be very upset with the ...

Begging for a Job

It is very common in Brazil that a job candidate will have the final ...

WordPress database error: [Table './brazzil3_live/wp_wfHits' is marked as crashed and last (automatic?) repair failed]
SHOW FULL COLUMNS FROM `wp_wfHits`