Brazil Wants to Restart Work on Nuclear Plant Paralyzed in 1988

The director of Planning, Management and Environment at Eletronuclear – the Brazilian company that operates the Angra 1 and 2 nuclear power plants – LuÀ­s Hiroshi Sakamoto, says that Brazil will need another nuclear power plant to meet the demand.

That nuclear power plant is Angra 3, which, along with Angra 1 and 2, went into construction during the military administrations (1964-85).

Angra 1 and 2 have been completed and are operational, but Angra 3, scheduled to be operating in 1988, was never finished although US$ 750 million was spent on it.

It is estimated it costs US$ 20 million just to maintain it in its present state, and will take another US$ 1.8 billion and five years to complete.

All three of Brazil’s nuclear power plants are located closely together at a beach resort, Angra dos Reis, on the coast of the state of Rio de Janeiro 150 kilometers from the city of Rio de Janeiro.

Sakamoto points out that because they are clean, the use of nuclear power plants around the world means that two billion tons of carbon dioxide have not been pumped into the atmosphere, aggravating the greenhouse effect.

As for Angra 3, Sakamoto says Brazil has the know-how to conclude the construction and is ready to do so. "The country is going to need more energy and Angra 3 is an obvious candidate to supply it," he said.

The Brazilian official added that the fact that construction on it has already begun is a positive point. "What has been paid for is paid for. We will move ahead from where we are. There is no need to start from scratch. It means building Angra 3 will cost less than a similar plant anywhere in the world."

Sakamoto says that at the moment nuclear power (Angra 1 and 2) supplies 40% of the electricity used in the state of Rio de Janeiro. With Angra 3 in operation, that percentage will rise to 70%.

Agência Brasil

Tags:

  • Show Comments (0)

Your email address will not be published. Required fields are marked *

comment *

  • name *

  • email *

  • website *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Ads

You May Also Like

Brazilian Furniture Exporters Have Big Plans for the Emirates

The United Arab Emirates will be one of the targets of Brazilian furniture exporters ...

What Was Brazil’s Role in Operation Condor? It Created and Led the Murderous Plan

The head of Brazil’s Justice and Human Rights Movement, Jair Krischke stated before the ...

Trade Unions from 27 Countries Gather in Brazil to Trade Ideas

Tunisian General Labor Union’s secretary general, Abdessalem Jerad, and the assistant secretary to the ...

Brazil’s Romário in ‘Six Chickens and a Raging Bull’

Fluminense’s president, David Fischel, criticized football star Romário for attacking a fan after a ...

Brazil’s Lula in Paraguay for Mercosur Summit

Brazilian President Luiz Inácio Lula da Silva is in Assuncion, Paraguay, for the 28th ...

Unemployment and Violence Two Main Worries of Brazil’s Youth

Young people in Brazil, between the ages of 15 and 24, are mainly worried ...

July 1994

CONTENTS: Cover: ABC & philosophy (p. 7) Now we pay in real (p. 13) ...

Brazil and South Korea Sign US$ 4 Billion in Deals

Brazilian and South Korean institutions and enterprises signed this Tuesday, May 24, in South ...

Bolivia Says It Will Respect Accords with Brazil, But Gas Prices Will Go Up

The president of Bolivia’s government hydrocarbons corporation YPFB, Jorge Alvarado Rivas guaranteed gas supplies ...